Project Manager – Ray Santangelo/Neil Patel
Construction Manager – Groom Construction
Construction Start – May 22, 2018
Construction Completion – August 15, 2018

The goal of this project is to identify under-utilized bedroom space on campus and add new beds, creating additional capacity for Tufts students to live on campus.  The rooms affected are typically oversized for the current occupancy, and can comfortably house an additional student while maintaining the same quality of life standards expected in all other rooms.  Construction includes minor relocations of walls or doors, and the addition of electrical outlets and data jacks.  A new, efficient bedroom furniture package will be installed in the rooms, helping to improve comfort for the students.  The project will be executed to varying degrees in Hodgdon, Harleston, Haskell, Metcalf, 32 Dearborn Street, and Hill Hall.  The work will include the addition of new bathrooms in Hodgdon and Harleston to accommodate the increased occupancy.

 

Construction Update – August 9, 2018

  • Harleston – Final flooring and painting is ongoing. Inspections are expected to take place this week.
  • Bush – Final inspections are expected to take place this week.
  • Hodgdon – Electrical and final inspections will take place this week.
  • Hill – Work is nearing completion.  Inspections are expected to take place this week.
  • 32 Dearborn – Work is nearing completion.  Inspections are expected to take place this week.
  • Haskell – Exterior façade work has been completed. Installation of roof flashing will be complete by August 10th, after which punch list items will begin. Landscaping at the front entry has been completed, except for the installation of sod, and landscaping at the rear entry is ongoing. Inspections will begin this week and MEP systems are set to be complete by August 17th.