Project Manager – Mike Skeldon
Construction Manager – JF White
Construction Start – May, 2018
Construction Completion– August, 2018

A chilled water line will be installed in the middle of the upper campus green. Road closures and detours will be required. A laydown area for materials will be needed to assist with the installation. This work will require frequent trucking, signage will be posted for detours and to assist with vehicular traffic from East Hall over to Olin Crossing on Packard Avenue. The work will be done in multiple phases over the course of the summer. Estimated project start is May, 2018 with estimated completion,  August, 2018.

 

Construction Update – August 9, 2018

  • The chilled water line installation will be complete by Friday, August 17th, as well as restoration of the walkways and landscaping.