Construction Update – August 23, 2018

  • Installation of drainage both around Halligan Hall / Cousen’s Gym and in the Parking Lot on the south side of College Ave is underway. It is expected a majority of this work will be completed by early September.
  • Demolition of 177 College Ave is scheduled for late next week, however the demolition of 179 College Ave will be done in the Fall, after the gas line is disconnected from 179 College Ave.