Project Manager – Chris Baryluk
Construction Manager – Timberline Construction
Construction Start – May 22, 2018
Construction Completion – August 15, 2018

Metcalf Hall will be undergoing the second and final phase of its long-planned building renewal.  Following exterior repairs completed in 2016, the summer 2018 project will include renovation to the lobby, hallway, and lounges.  The basement will be renovated to add 10 new student beds.  All student room doors will be replaced, along with installation of new electronic locks.  The design of the interior finishes will pay tribute to the styles indicative of the building’s long history, while introducing fresh and vibrant themes from modern day.

 

Construction Update – July 12, 2018

  • All lighting circuits have been rewired to correct unforeseen existing conditions
  • New doors have been installed throughout
  • Acoustic ceiling grids are being installed
  • Flooring will begin later this week
  • Electric locks will begin installation in two weeks.